Overview
Pouring a flatwork concrete slab for a backyard shed, workshop, or ground-level extension requires matching slab thickness to expected loading conditions and preparing perimeter formwork and sub-base materials. This Concrete Slab Calculator computes necessary concrete volume using standard thickness presets while generating separate line-item estimates for crushed gravel, vapor barriers, and rebar.
Estimates are for material planning and budgeting purposes only. This calculator does not provide structural engineering, architectural design, or official building code compliance advice. Always verify measurements, local building codes, and permit requirements with a licensed contractor or local building authority before purchasing materials or commencing construction.
Worked Examples
Example 1: Standard 12 ft × 10 ft Shed Slab (4 in Thick with 10% Waste)
Inputs: Length = 12 ft, Width = 10 ft, Preset = 4.0 in, Waste = 10%, Reinforcement = #4 Rebar at 18" Grid
- Convert thickness: 4 in ÷ 12 = 0.3333 ft.
- Calculate net cubic feet: 12 ft × 10 ft × 0.3333 ft = 40.00 cu ft.
- Convert to cubic yards: 40.00 cu ft ÷ 27 = 1.48 cu yd.
- Add 10% waste reserve: 1.4815 cu yd × 1.10 = 1.63 cu yd.
- Round UP to supplier 0.25 yd increment: 1.75 cu yd.
- Calculate separate 4" gravel base: 120 sq ft × 0.333 ft ÷ 27 = 1.48 cu yd (approx. 2.22 tons).
Final Answer: 1.75 cu yd to order (1.48 net cu yd; 2.22 tons gravel base; 44 linear ft forms)
Example 2: Heavy Workshop Slab (20 ft × 15 ft at 6 in Thick)
Inputs: Length = 20 ft, Width = 15 ft, Preset = 6.0 in, Waste = 10%, Reinforcement = #4 Rebar at 12" Grid
- Convert thickness: 6 in ÷ 12 = 0.50 ft.
- Area: 20 × 15 = 300 sq ft; Net volume: 300 × 0.50 = 150.00 cu ft.
- Cubic yards: 150.00 ÷ 27 = 5.56 cu yd.
- Add 10% waste: 5.5556 × 1.10 = 6.11 cu yd.
- Round UP to ready-mix increment: 6.25 cu yd.
- Perimeter forming boards: 2 × (20 + 15) = 70 linear ft (2×6 lumber).
Final Answer: 6.25 cu yd to order (5.56 net cu yd + 0.56 waste reserve; 70 linear ft formwork)
Example 3: Sidewalk / Walkway Slab (30 ft × 4 ft at 3.5 in [Nominal 2×4])
Inputs: Length = 30 ft, Width = 4 ft, Preset = 3.5 in, Waste = 8%, Reinforcement = WWM
- Convert thickness: 3.5 in ÷ 12 = 0.2917 ft.
- Area: 30 × 4 = 120 sq ft; Net volume: 120 × 0.2917 = 35.00 cu ft.
- Cubic yards: 35.00 ÷ 27 = 1.2963 cu yd.
- Add 8% waste factor: 1.2963 × 1.08 = 1.40 cu yd.
- Round UP to next 0.25 yd: 1.50 cu yd.
Final Answer: 1.50 cu yd to order (1.30 net cu yd; 68 linear ft 2×4 forms)