Overview
Accurately quantifying total working days between two dates is essential for project sprint estimation, construction staffing, manufacturing production scheduling, and freelance retainers. The Working Days Calculator computes the net working days and total productive hours between any two dates.
This calculator supports standard 5-day workweeks (Monday–Friday) as well as 6-day commercial schedules (Monday–Saturday). It excludes weekend days and computes total billable hours based on your configured workday length. Please note that public holidays are not included in this calculation.
Worked Examples
Example 1: Month of January 2026 (5-Day Workweek, 8 Hours/Day)
Start: 2026-01-01, End: 2026-01-31, Workweek = 5-Day, Hours = 8
- Total calendar days: 30 days between Jan 1 and Jan 31.
- Weekend days in January 2026 (Saturdays and Sundays): 8 days.
- Working days: 30 − 8 = 22 working days.
- Total work hours: 22 × 8 = 176 hours.
Final Answer: 22 working days (176 total hours)
Example 2: Same Span with 6-Day Workweek (Mon–Sat)
Start: 2026-01-01, End: 2026-01-31, Workweek = 6-Day, Hours = 8
- Only Sundays are excluded: 4 Sundays.
- Working days: 30 − 4 = 26 working days.
- Total work hours: 26 × 8 = 208 hours.
Final Answer: 26 working days (208 total hours)
Example 3: Two-Week Sprint (March 2, 2026 to March 16, 2026)
Start: 2026-03-02 (Monday), End: 2026-03-16 (Monday), 5-Day Week
- 14 calendar days total.
- Saturdays and Sundays: 4 weekend days.
- Working days: 14 − 4 = 10 working days.
- Work hours: 10 × 8 = 80 hours.
Final Answer: 10 working days (80 total hours)