Overview
Calculating structural foundation concrete demands computing continuous perimeter strip footings alongside isolated interior pier pads and column footers. This Concrete Footing Calculator computes dual-geometry footing requirements with explicit depth conversions and an over-excavation waste reserve.
Estimates are for material planning and budgeting purposes only. This calculator does not provide structural engineering, architectural design, or official building code compliance advice. Always verify measurements, local building codes, and permit requirements with a licensed contractor or local building authority before purchasing materials or commencing construction.
Worked Examples
Example 1: Continuous Strip Trench with 4 Pier Pads (Check Case)
Inputs: Trench Length = 50 ft, Width = 16 in, Depth = 8 in, Piers = 4 (24"×24"×12"), Waste = 10%
- Convert strip dimensions: Width = 16 ÷ 12 = 1.3333 ft; Depth = 8 ÷ 12 = 0.6667 ft.
- Calculate strip footing volume: 50 ft × 1.3333 ft × 0.6667 ft = 44.44 cu ft = 1.646 cu yd.
- Calculate single pier pad: (24÷12) × (24÷12) × (12÷12) = 2 ft × 2 ft × 1 ft = 4.00 cu ft.
- Calculate 4 pier pads: 4 × 4.00 cu ft = 16.00 cu ft = 0.593 cu yd.
- Sum net volume: 44.44 + 16.00 = 60.44 cu ft ÷ 27 = 2.239 cu yd.
- Add 10% trench waste: 2.2387 × 1.10 = 2.4625 cu yd.
- Round UP to next 0.25 cu yd truck increment: 2.50 cu yd.
Final Answer: 2.50 cu yd to order (1.65 strip cu yd + 0.59 pier cu yd; exact unrounded: 2.46 cu yd)
Example 2: Perimeter Strip Footing Only (100 ft × 20 in × 10 in with 12% Waste)
Inputs: Trench Length = 100 ft, Width = 20 in, Depth = 10 in, Piers = 0, Waste = 12%
- Convert trench width and depth: Width = 20 ÷ 12 = 1.6667 ft; Depth = 10 ÷ 12 = 0.8333 ft.
- Calculate volume: 100 × 1.6667 × 0.8333 = 138.89 cu ft.
- Convert to cubic yards: 138.89 ÷ 27 = 5.1440 cu yd.
- Add 12% trench over-dig allowance: 5.1440 × 1.12 = 5.7613 cu yd.
- Round UP to supplier increment: 6.00 cu yd.
Final Answer: 6.00 cu yd to order (5.14 net cu yd + 0.62 waste reserve; 6.00 cu yd ordered)
Example 3: Heavy Deck Footings (6 Pier Pads at 30" × 30" × 12" Deep)
Inputs: Trench Length = 1 ft (minimal), Width = 12 in, Depth = 6 in, Piers = 6 (30"×30"×12"), Waste = 10%
- Single pier pad: 2.5 ft × 2.5 ft × 1.0 ft = 6.25 cu ft.
- Total 6 pads: 6 × 6.25 cu ft = 37.50 cu ft = 1.3889 cu yd.
- Add 10% waste buffer: 1.3889 × 1.10 = 1.5278 cu yd.
- Round UP to next 0.25 yd: 1.75 cu yd.
Final Answer: 1.75 cu yd to order (1.39 net cu yd for pier pads; 1.75 cu yd ordered)